Essential Gas Main Replacement Works in Upper Richmond Rd Putney SW15

 

Phase three: 16th May – 6 th September 2011

Related Articles

Local Road and Travel Information

Participate
Sign up for our free weekly newsletter

Comment on this story on the

Works will begin on Monday 16 May and are scheduled to run for 11 weeks to Tuesday 6 September, although everything possible will be done to shorten this period.

As a result of these works Upper Richmond Road will be made one way eastbound from Wandsworth County Court to the junction of West Hill, with westbound traffic being diverted via West Hill, Tibbets Corner and Putney Hill.

At the beginning of the works Keswick Road will be closed for 3-4 weeks. Once Keswick Road has re-opened Oakhill Road will be closed for approximately 3-4 weeks.

No other roads are scheduled for closure during these works. There will be a signed cyclist diversion route via Putney Bridge Road, Fawe Park Road and Oxford Road.

The works will be carried out seven days a week within the following timeframes:

Monday to Friday - 8.00am - 10.00pm (no noisy work after 6pm)
Saturday - 8.00am - 4.00pm (no noisy work after 1pm)
Sunday - 9.00am - 1.00pm (no noisy work on this day)

 

April 27, 2011