Tideway Tunnel Reaches Putney Bridge
Tunnelling machine 'Rachel' completes over 20.5% of her journey to Acton from Fulham



Participate

Sign up for our weekly Putney newsletter

Comment on this story on the

Rachel began her journey in May and is on her way to complete the 7km journey to our Acton Storm Tanks site. This week she arrived in the vicinity of Putney Bridge approximately 1388km (20.57%) into her journey.



On the surface, all efforts are focused on supplying Rachel with ring segments and removing excavated material by barges, since August 2019 three barges have removed spoil from Putney site. Each barge is the equivalent50 HGV lorries not traveling on local roads. A total of 17 barges have been used since the project started.


A section of the tunnel under the river

November 1, 2019

Bookmark and Share